DBM Bridges
Building Bridges and Structures for the future.
Home
Projects +
Project 1 Dish Hill Flyover
Project 2 Church Road Footbridge
Project 3 Bingham Railway Bridge
Project 4 Argyle Street Hull
Project 5 Micklefield Demolition
Project 6 Fairburn Footbridge
Project 7 Fairburn Railway Bridge
Project 8 Micklefield Railway Bridge
Project 9 Lumby Leys Bridge
Project 10 Lunfield Lane
Project 11 CTL3 Waterworks Tip
Project 12 Upper Brow Road
Project 13 Nineveh Road
Project 14 Church Lane Footbridge
Project 15 Hillidge Road
Project 16 Waterloo Road Footbridge
Project 17 North Road Bridge
Project 18 Moor Road Railway Bridge
Project 19 Hunslet Moor Footbridge
Project 20 Holmfield Demolition
Project 21 Convicts Wood Bridge
Project 22 Clapham Hill Bridge
Project 23 Potters Bar
Project 24 Barrow Hill Demolition
Project 25 Blue Gowt
Project 26 Folly Bridge Footbridge
Project 27 Ben Ryhdding Footbridge
Project 28 Willow Bank
Project 29 Stubbin Lane
Project 30 Thompson Street Darlington
Project 31 Network Rail SPM Dairycoats Hull
Project 32 Network Rail SPM River Nene.
Project 33 Network Rail SPM James Reckitt Avenue Hull
Project 34 Network Rail SPM Market Weighton Brough
Project 35 Network Rail SPM AFA Metro
Project 36 Network Rail SPM Selby Swing Bridge Span 1
Project 37 Barnabus Road London
Project 38 STF6 & STF7 Carlton/Thorpe Road Stockton
Project 39 Selby Fork Demolition
Project 40 E58 Brotherton Fox
Project 41 Walshford Bridge
Project 42 River Aire Bridge
Project 43 Knottingley Road
Company Links
Home
Project 7 Fairburn Railway Bridge
View on the existing Railway Cutting - topsoil part stripped on the North side.
View on the existing Railway cutting prior to works starting for the new structure.
Works progressing with reinforced Earth walls under construction on the North side and Bulk dig in progress on the south side.
Bottom Reinforced Earth panels being set up and clamped together with timbers and tie rods.
Excavated material being crushed and graded for placement in the reinforced earth.
Crushed material being placed to the reinforced earth.
Reinforced Earth erected - View on the North Abutment with reinforcement being fixed for the abutments.
South Reinforced earth being erected - scaffold hand rail being installed for edge protection.
Cranes working behind the North abutment - with steel fixing and concrete progressing to the abutments.
South Abutment - formwork being erected for the abutment bearing shelf.
Main bridge beams being delivered to site for off loading.
Bridge beams being off loaded and laid out ready for the main possession.
Concrete edge beams delivered to site and set up on temporary concrete stillages.
Parapet posts and sheets being installed ready to be lifted in with the concrete parapets.
Works progressing on the abutment wingwalls - steel fixing well progressed.
Formwork being stripped from the main body of the abutment complete.
West End Parapet with Edge parapet installed.
700t Crane lifting in the Parapet edge beam landed.
Typical beam being lowered down onto the elastomeric bearings and temporary supports.
Concrete cubes used to take the load while the epoxy mortar on the elastomeric bearings hardens and cures.
Looking on as the East end parapet is lifted and landed in the possession.
Crane installing the infill concrete beams during the possession note the crane position has moved.
Bob Meadows landing the final concrete beam next to the outside East Edge beam.
GRP formwork being installed during normal working - T(ii's) taken where required to install the GRP over the track.
GRP being installed - steel fixing to the diapraghms being installed.
GRP installed - lifting loops cut off and reinforcement fixing progressing.
Steel reinforcement being fixed on the deck - deck being sealed.
Steel reinforcement being lifted onto the bridge deck - Formwork being fixed to the first of 4 pours.
First Quarter of the bridge deck cast with the second quarter being set up for concrete.
Half the bridge cast - Steel reinforcement nearly fully fixed - Wingwall parpet being set up.
Third quarter of bridge deck being cast - note the stop end. The track below is open to traffic.
Three quarters of the bridge cast - final quarter being set up for casting.
The fourth and final quarter of the bridge deck being cast.
Remaining wingwalls being cast with a concrete pump.
Snow hits progress - formwork being set up on the bridge.
Snow clear - with concrete cast on the deck - steel being fixed at the difficult corners.
View from the air looking down on the bridge deck.
Spray waterproofing being undertaken on the diapraghm - ready for backfilling.
Sand Carpet laid over the waterproofed deck.
Temporary access created over the bridge - sand layer run over the bridge for construction traffic.
Carriage way being created over the bridge. Existing A1M running in the North East Corner of the Photo.
Temporary road being constructed in the back ground temporary road running over the bridge.
Carriage way under construction over the bridge. Footpaths being concreted.
South Bound A1M diverted over onto the bridge carriageway - Note A1M existing south bound closed and being planned out.
Both the North and South carriageways moved over onto the temporary carriage way over the bridge. Works started on the new structure Brotherton Ings.
Works progressing on Brotherton Ings bridge and main carriageway under the bridge.
Looking over Fairburn Railway bridge up to Brotherton Ings bridge- New A1M carriageway close to being ready to open.
New A1M completed road open with traffic switched onto the final alignment over the new structure.
Client – Highways Agency
Contractor – RMG - Alfred McAlpine, Dragados, KBR, AMEC
Agent – Bob Meadows
Sub Agent – David Millar
Reinforced Earth – Gatwick Rail LTD (no longer trading)
Civils – Reinforcement, Concrete, Formwork- Sword Construction
Cranes – Emsley Crane Hire, Ainscough Heavy Crane Hire
Precast concrete – Buchan precast
Parapets – Balmer Lindley
Reinforcement – ROM Ltd
EMJ Plastics – Perment Formwork
Concrete Pump – Pochin
Bearings – Ekspan
McAlloy Bars – Macalloy bars and fixings
Waterproofing – Stirling Lloyd
Page under construction...