|
Home | | | | Project 17 North Road Bridge | |
|
|
|
![View on the location of the Proposed North Bridge](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10004_.jpg)
View on North bridge prior to works starting on the new bridge.
![North Bridge South Abutment. M621 Off Slip](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10007_.jpg)
View looking toward the proposed south abutment of the New North Bridge.
![North Bridge North Abutment.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10006_.jpg)
View on the North proposed abutment location - Note the wide access between the fence and the wall.
![North abutment Dig in progress](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10023_.jpg)
Work started on the North abutment - works in progress excavation in progress.
![North abutment dig complete](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10056_.jpg)
Bulk dig to the North abutment - terrace greated for crane platform.
![Drilling and grouting in progress North abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10068_.jpg)
Drilling and groutin in progress to the North Abutment.
![Grouting being undertaken on the North abutment.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10075_.jpg)
Grouting being undertaken to the voids in the North abutment.
![North abutment grouting on the approaches](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10088_.jpg)
Drilling and grouting in progress on the North abutment.
![South Abutment lane closure and gas diversion works](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10105_.jpg)
Gas main being diverted on the slip road.
![Extensive gas diversion works.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10125_.jpg)
Gas main valve connecetion being connected up and encased in concrete.
![Cable trough and fence installed at track level.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10131_.jpg)
Works in progress at track level - S&T Trough route diverted to enable the abutment construction.
![Martello Piling start piling the North Abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10136_.jpg)
Martello piling carrying out the pile installation on the North abutment.
![South Abutment dig being started](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10137_.jpg)
Excavation to the South abutment - view on the fence at track level and S&T.
![North abutment piling being undertaken](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10146_.jpg)
Martello piling lifting and installing piles using a mini crane.
![Vario Guard installed on the south abutment.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10152_.jpg)
Vario -Guard installed up the Jun 4 Slip road.
![Vario Guard installed and dig started - old gas main in the dig](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10160_.jpg)
Excavation being undertaken behind the barrier - note the redundant gas main in the excavation.
![Dig on going on the South Abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10180_.jpg)
Excavation in progress - ramp created down to track level.
![North Abutment piling complete.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10175_.jpg)
North abutment piles installed ready for digging out.
![Bulk dig on the South Abutment shows the coal measures.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10194_.jpg)
Southern abutment - coal strips in the dig require removed.
![Bulk Dig and piling completed](http://www.dbmbridges.com/web_images/north_bridge_-_plane.jpg)
View on the excavation for both the North bidge and Moor road.
![Pile break down](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10209_.jpg)
Piles being broken down using a pile breaker.
![North abutment blinded and steel fixing in progress.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10222_.jpg)
Piles broken down - blinded and steel being fixed.
![Dig removing the coal measures and fill in bays.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10240_.jpg)
Coal measures being excavated out and removed.
![Works progressing on the south abutment.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10274_.jpg)
Coal measures being excavated out - the seam had been worked to the fill was also excavated and filled with concrete.
![North Abutment Crawler crane lifting in reinforcement and formwork](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10287_.jpg)
North abutment steel reinforcement being fixed with Forwork being installed to the base.
![South abutment mothballed while work progress on the North abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10285_.jpg)
Southern abutment fully excavated - water filled - works put on hold until the new year.
![North Abutment Cast and back filling in progress](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10300_.jpg)
North abutment blackjacked and backfilled with 6N.
![Steel fixing starting on the South Abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10322_.jpg)
Base blinded with concrete - steel fixing started to the base.
![South Abutment progressing with crane lifting shutters](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10333_.jpg)
Steel fixed to the base - formwork base shutters moved round form the North ready for reuse. crane set up ready for lifting.
![South Abutment base being cast.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10337_.jpg)
South base being concreted - concrete pump on the crane platform.
![South Abutment base backfilled with Reinforcement being delivered.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10361_.jpg)
Base cast and being backfilled - steel reinforcement being set up for fixing the abutment wall.
![North Abutment wingwall being cast with concrete pump](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10359_.jpg)
North abutment - formwork set up - wingwalls being cast with a concrete pump.
![North Abutment formwork being erected.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10369_.jpg)
Wingwall cast with formwork being set up for the main wall pour.
![South Abutment Scaffold being erected.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10370_.jpg)
All the work being undertaken during normal working - Scaffold being erected to enable steel fixing.
![Heidi Simpson Engineer working on the Abutment](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10380_.jpg)
Heidi Simpson setting out bearing plinths on the abutments.
![North Abutment being cast.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10388_.jpg)
North abutment being cast during normal working with a concrete pump.
![Abutments under construction](http://www.dbmbridges.com/web_images/north_bridge_-_plane__1_.jpg)
View on the abutment construction both well underway.
![North Abutment formwork removed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10416_.jpg)
North abutment & wingwalls cast - concrete finishing in progress.
![South Abutment set cut to be cast.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10453_.jpg)
Southern abutment - formwork being set up using a mobile carne.
![Henry Woodhead and Heidi setting up the bearings](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10452_.jpg)
Henry and Heidi - setting up the bridge bearings on the North abutment.
![North Abutment Bearings Set and Scaffold removed](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10458_.jpg)
Scaffold removed from the North abutment - backfilling in progress.
![South Abutment Cast with formwork removed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10459_.jpg)
Concrete completed - Mobile crane lifting out formwork.
![Bearing plinths set up on the abutment Note pockets.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10465_.jpg)
South abutment - bearing blinths cast with pockets prepared for bearings.
![North Abument Backfilled and crane outrigger points set out.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10472_.jpg)
North abutment - backfilling being undertaken ready for the crane to being rigged for lifting.
![Steel beams arrive on site and are parked up](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10478_.jpg)
Beams on site ready for lifting - they are on site in braced pairs.
![Beams lifted into place and set.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10482_.jpg)
Steel beams erected in possession with GRP installed to two of the sets.
![Braced pair installed with tapes but not panels](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10485_.jpg)
View along the girders - tape and sealing strip installed along the top flange for fixing the GRP panels.
![1st stage grout to the bearings.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10486_.jpg)
Bridge beam lifted in and set up on the bearings. Note the red transit brackets.
![GRP viewed from below on the braced pairs.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10489_.jpg)
View from below the beams - note the GRP panels follow the curve and are set with a gap to follow the curve.
![GRP installed on the bridge.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10493_.jpg)
GRP - panels - supplied by EMJ fixed in place (by lift reinforcement bars) panels installed during possession.
![Multiforms installed during normal working in the corners.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10506_.jpg)
Multi-forms being erected - corner units installed during normal working.
![Multiforms Installed after the week end possession.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10507_.jpg)
Multiforms - installed during possession.
![Multiforms installed work progressing on the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10517_.jpg)
View on the East parapet with multiforms installed work progressing on the deck during normal working.
![Steelfixing to the Diapraghm.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10524_.jpg)
Soffit of the diapraghm installed - steel fixing in progress.
![Reinforcement being fixed on the diapraghm + formwork to the inside face.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10530_.jpg)
Formwork installed to the inside face of the diapraghm. - steel fixed being fixed.
![North abutment diapraghm being cast.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10537_.jpg)
Works in progress to the gabion baskets infill behind the new stone infill walls.
![Infill stone walls being reconstructed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10557_.jpg)
Stone walls being installed infront of the Gabion baskets.
![Reinforcement being fixed on the deck.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10563_.jpg)
The multiforms were faced up with good quality ply - steel fixing in progress.
![Diapraghm cast and formwork removed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10577_.jpg)
Diapraghm cast ready for GRP to installed.
![Scaffold infront of the abutment with Hook Bolts](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10581_.jpg)
View on the North abutment - with scaffold ereceted for access to the bearing shelf.
![Steel fixing on going on the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10589_.jpg)
Steel fixing at deck level.
![H4a Bolt sets being set + stop end being installed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10597_.jpg)
Deck reinforcement set up on the deck - Note the H4a bolts set up on the parapet.
![Concrete being placed to the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10627_.jpg)
Bridge deck being cast during normal working (yes the trains were running)
![Deck being cast concrete pump moved to the South abutment.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10634_.jpg)
Deck being cast with the concerte pump on the Southern abutment.
![Concrete pump placing concrete on the bridge deck with the track open below.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10637_.jpg)
Deck being cast during normal working.
![Parapet formwork being set up on the deck.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10649_.jpg)
Parapets being set up for casting - note the H4A bolt clusters.
![Parapet formwork set up - loads designed to transfer into the multiform](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10662_.jpg)
Parapet - formwork shutters being set up the design allowed for timbers fixing onto the parapet.
![East Parapet being set for casting.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10670_.jpg)
Parapet set up ready fro concrete.
![Bridge Parapets cast and stripped out.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10678_.jpg)
Parapet cast and stripped out ready for concrete finishing.
![Progress on going on the wingwalls.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10754_.jpg)
South abutment formwork being lifted into place.
![Soffit of the inspection Gallery being set up](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10781_.jpg)
Gallery soffit falsework being installed.
![Reinforcement being fixed at the end of the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10797_.jpg)
Soffit of the Deck nib set up with plywood - steel being fixed to the deck end.
![C frame on site and J clamp hand rail being set up.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10799_.jpg)
SGB - steel lifting frame - combi-safe fence being installed along the parapets.
![Tower crane lifting down the multiforms.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10806_.jpg)
Railway possession - self erecting tower crane being used to lift out the multiforms.
![Multiforms removed over the majority of the bridge.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10810_.jpg)
Multiforms removed over the central deck - South side not removed as the parapets had not been completed.
![Multiforms removed.](http://www.dbmbridges.com/web_images/north_bridge_-_plane__3_.jpg)
View on the bridge deck after casting and muliform removal.
![Deck steel fixed ready for concrete.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10839_.jpg)
South deck nib set up for casting.
![Screen wall capping section being concrete to create the expansion joint.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10864_.jpg)
North abutment gallery nib being cast by Swords.
![Waterproofing to the North Abutment in progress.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10898_.jpg)
Brick access manhole installed - Stirling lloyd spray waterproofing to the abutments ready for backfilling.
![South Abutment Concrete completed with access manhole being constructed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10905_.jpg)
South abutment - access manhole being constructed with blue bricks.
![Works ongoing at the corners of bridge.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10924_.jpg)
South abutment - parapets completed and multiform/scaffold removed - backfilling in progress.
![H4a Parapets being installed on the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10926_.jpg)
Frost on the deck - H4a parpets being erected on the deck.
![M621 approach wall being constructed to tie in to the bridge](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10945_.jpg)
South abutment approach retaining wall base being set up on blinding ready for formwork.
![Approach wall being constructed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10953_.jpg)
Approach base - set up with steel fixed in the wall - Formwork set and base cast.
![Approach wall cast.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10966_.jpg)
Retaining wall cast.
![Bridge Deck waterproofed](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10974_.jpg)
Bridge deck spray waterproofed and tack coated - Note the access slab cast on top of the blue brick manhole.
![H4a Parapets installed.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10984_.jpg)
View on the East parapet - note the new wall built on the South abutment.
![Red Sand carpet on the bridge.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__10990_.jpg)
Sand carpet laid on the bridge deck - note the timbers fixed into the joints.
![Rolling block installed at the end of the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11006_.jpg)
Run on slabs formed on the approach to the structure. The run on slabs were formed free had by excavator.
![Deck dparture roads works in progress.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11036_.jpg)
Construction of the road formation and kerbs on the North abutment.
![Black top being laid on the deck](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11046_.jpg)
Surfacing being laid over the bridge - H4a installed but not sheeted. Footpaths being concreted.
![Bridge Joints being installed by USL](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11077_.jpg)
USL installing bridge expansion joints.
![Road over the bridge being created](http://www.dbmbridges.com/web_images/north_bridge_-_plane__4_.jpg)
View on the new bridge.
![Weekend road switch over the bridge.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11113_.jpg)
48hr Week end blockage swapped the traffic over onto the new road alignment.
![Bridge open under traffic management](http://www.dbmbridges.com/web_images/north_bridge_-_plane__5_.jpg)
View on the bridge with the new road alignment.
![Sheets added to the H4A with the bridge fully open.](http://www.dbmbridges.com/web_images/project_no_17_-_m621_north_bridge__11154_.jpg)
View on the bridge showing the parapets fully sheeted in - grass being cut for full opening.
![Completed bridge and Junction 4 works.](http://www.dbmbridges.com/web_images/north_bridge_-_plane__6_.jpg)
Completed junction 4 open to traffic.
Page under construction...
| |
| | |
|
|
|
|
|