|
Home | | | | Project 19 Hunslet Moor Footbridge | |
|
|
|
![Hunslet Moor old structure](http://www.dbmbridges.com/web_images/project_no_16_-_lirr7_hunslet_moor_footbridge__200001_.jpg)
Existing Footbridge over the M621 Between Jun 4 & Jun 5.
![Pile locations in existing road](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10000_.jpg)
View from the existing footbridge looking up Moor Road - Piles marked on the road.
![Existing Bridge central ramps being removed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10009_.jpg)
Existing Bridge central ramp removed during an over night closure.
![Central ramp being moved and reerected](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10012_.jpg)
Central ramp removed and re-erected on exiting trestles at the North end of the bridge.
![Old Footbridge Ramp switched + crane removal](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10017_.jpg)
Existing ramp being removed -to make way for the new abutment.
![Abutment Dig underway](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10031_.jpg)
Sheet piles installed and the abutment being excavated out.
![Abutment reinforcement being fixed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10037_.jpg)
Steel fixed to the base. Formwork installed ready for concrete.
![Base Cast - Ramp foundation](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10057_.jpg)
Ramp reinforcement being fixed - North abutment base cast and bearing shelf set up for concrete.
![Ramp founation being set up](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10064_.jpg)
North abutment base and shelf cast - ramp base steel reinforcement fixed formwork being set up for concrete.
![Concrete walls set up](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10081_.jpg)
North abutment & ramp concreted ready for backfill and steel work.
![Road laid + lighting mast](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10083_.jpg)
High Mast lighting tower installed in possession.
![Back fill to the embankment](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10086_.jpg)
South abutment fill being placed to the embankment (basra) bridge access service ramp area.
![Abutment steel being fixed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10087_.jpg)
South abutment steel fixing in progress.
![Moor Road Open traffic switched](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10107_.jpg)
North abutment & Ramp black jacked ready for filling.
![Abutment crane lifting formwork](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10109_.jpg)
Crane on the South abutment erecting formwork.
![Piling platfrom being created](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10117_.jpg)
Piles set out for the central pier foundation.
![Expanded Piling](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10129_.jpg)
Expanded pilig drilling the piles - crawler lifting the reinforcement cages.
![Abutment under construction](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10132_.jpg)
Southern abutment - bearing shelf cast - wingwalls being set up with formwork.
![Piles exposed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10152_.jpg)
Piling complete to the central pier base. Piles broken down and blinded. Steel on site ready for fixing.
![Central pier base being cast](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10158_.jpg)
Bridge central pier base - formwork set up and concrete being placed.
![Central Pier upper section being cast](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10164_.jpg)
Top section of the central pier being cast. Note self erecting tower crane.
![Self erecting tower crane](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10183_.jpg)
Self erecting tower crane lifting out formwork - sat in the M621.
![Central Pier bolt clusters](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10193_.jpg)
Top section of the Central pier - bolt clusters set in place using the holding plate.
![Central pier cast just in time](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10215_.jpg)
Central pier formwork removed - and backfill - Nusteel on site ready to start.
![Cranes landing A frame](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10229_.jpg)
Two 100T Cranes unloading and setting up the steel work A- Frame
![Steel A frame set in place](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10231_.jpg)
Steel A frame laid out on the ground around the central pier.
![Ramo steel work being installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10248_.jpg)
Works progressing on site shift - moor road closed - trestles lifted in place.
![Ramps being installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10268_.jpg)
Work in progress installing the the ramps and North trestle.
![Abutment cast](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10301_.jpg)
North abutment - wingwalls parapet steel being fixed.
![Ramps being erected on nights](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10320_.jpg)
Crane lifting in the ramp units - with Moor road closed over night to traffic.
![Temporary works installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10334_.jpg)
Temporary works trestle installed ready for building the bridge.
![A frame being ereceted](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10342_.jpg)
Bridge pylon being lifted into place with a 500t crane.
![Connecting pins](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10374_.jpg)
Anchorage bolts for the cables delivered on site.
![Welded connection](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10375_.jpg)
Anchorage points welded on to the main bridge deck. These were installed on site due to wide load transport issues.
![Steel cables delivered to site](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10376_.jpg)
Bridge cables delivered to site and laid out - The cables being supplied by Bridon Ropes Doncaster.
![Deck unit being installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10383_.jpg)
Bridge deck section being lifted into place. This deck section was fitted onto the pylon and then onto the temporary tower.
![Cables being installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10386_.jpg)
Crane lifting and installing the cables. Full boom MEWP.
![Bridge just before christmas](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10393_.jpg)
First section of the bridge deck set in place with cables installed ready for the next unit.
![Backfilled abutment](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10403_.jpg)
Southern abutment completed and backfilled ready for steel erection.
![Bridge deck being erected](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10412_.jpg)
Crane erecting deck sections main crane holding the deck with a smaller crane lifting the cables.
![Temporary works being removed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10419_.jpg)
Temporary works trestle being removed following installation of the deck section.
![Temporary works being reinstalled](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10435_.jpg)
Temporary works trestle being re-erected infront of the south abutment.
![Connection Pin](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10441_.jpg)
Typical cable locking fixing pin.
![Cone added to pin](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10450_.jpg)
Spike attached to the fixing pin to assist installation.
![cable being lifted on clamp](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10443_.jpg)
Cable being lifted using a purpose made lifting clamp locked onto the cable.
![Cable being lifted by crane](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10444_.jpg)
Cable fully extended above the ground - MEWP installing the cables at top flange.
![Cable connector with spacer](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10454_.jpg)
Pin installed with anchorage - note the calliper to stop the pin dropping through the deck fixing.
![Crane holding deck section + crane holding cable](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10464_.jpg)
Crane holding the deck section as the support crane moves the cable across into position.
![Bridge section sat on the Temporary works](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10472_.jpg)
Deck section with cables installed - last section of deck sat on the trestle temporary works.
![Cable connecetors being drawn together](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10493_.jpg)
Cable eye being lifted and pulled into position with a chain block.
![cable and deck connectors aligned](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10497_.jpg)
Pin and eye aligned with pull chains allows the pin to be installed.
![Pin being installed between connectors](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10503_.jpg)
Locking pin being installed through the cable eye and pin.
![Last section in place with temporary works removed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10505_.jpg)
Deck fully instaled - temporary works support removed with the crane.
![Jacks installed at connector to tension the cables](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10529_.jpg)
Pins on the deck jacked out and nuts tightened to the correct tension.
![Deck ready for concrete](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10594_.jpg)
Bridge deck - completed - being clean off ready for concrete.
![Concrete to bridge deck](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10616_.jpg)
Swords operatives using a small 1t dumper to place concrete on the bridge deck.
![Concrete steps being installed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10676_.jpg)
On the South approach a crane is being used to install pre-cast concrete stair units.
![Concrete being captive blasted](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10717_.jpg)
Bridge deck is fully concreted with crack inducers installed across the deck to form bays.
![USL doing Bridge joint](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10723_.jpg)
USL instastalled the expansion joint on the south side of the bridge deck.
![Bridge approch](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10738_.jpg)
View on the southern approach with the earthworks complete and pre-cast concrete stairs installed.
![Bridge Deck with anti skid placed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10748_.jpg)
ROCAL installing Cicol to the bridge deck - grit put on the deck surface held in place with the epoxy resin.
![Old bridge being removed](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10754_.jpg)
With the new bridge open to the public - the final section of existing bridge deck was lifted out.
![Old bridge being taken down over the 621](http://www.dbmbridges.com/web_images/project_no_19_-_hunslet_moor_footbridge__10767_.jpg)
Existing structure being lifted down on to the M621 carriageway for breaking up and removal.
![Completed project from the air](http://www.dbmbridges.com/web_images/project_no_16_-_lirr7_hunslet_moor_footbridge__200007_.jpg)
View on the completed new bridge spanning 104m form the North abutment to the South abutment (basra area).
| |
| | |
|
|
|
|
|