|
Home | | | | Project 24 Barrow Hill Demolition | |
|
|
|
![Barrow Hill Bridge prior to work starting](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20004_.jpg)
Existing Barrow Hill Bridge and Footbridge.
![Bridge span over the Railway](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20003_.jpg)
View looking under the existing footbridge (to be retained) + Barrow Hill bridge to be demolished.
![Side Span being set up for underfilling](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20009_.jpg)
Existing bridge - Span to be underfilled with foam concrete.
![1st Stage set up for grout underfill](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20012_.jpg)
Side span - 1st lift of foam concrete - retained with mesh reinforcement and polythene.
![2nd layer of polythene and mesh set up ready for grout](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20016_.jpg)
Polythene sheet inside the mesh reinforcement ready for foam concrete.
![3rd Layer being set up with mesh being fixed.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20017_.jpg)
Next lift of underfill being set up for concrete.
![Grout infill](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20018_.jpg)
Foam concrete place as underfill to the 3rd Lift.
![Bridge fully underfilled.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20019_.jpg)
Completed underfill last lift poured through holes punched in the deck.
![Wingwall requires removed for the new structure](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20022_.jpg)
View on the completed underfill.
![Temporary works installed to remove the wingwall and retain the wall.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20052_.jpg)
Temporary works installed to retain the fill on the existing wingwall. The new structure under construction of the end of the wingwall.
![New structure under construction.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20062_.jpg)
New structure under construction - once this bridge is open then Barrow Hil Existing bridge can be demolished.
![Eckington Bridge open under traffic lights ready to allow the bridge demolition to start.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20090_.jpg)
Existing bridge open to traffic under traffic lights.
![Road Planner removing the old road.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20097_.jpg)
Existing Eckington Road being planned out - with the new road fully open.
![Cables and services previously diverted onto the new bridge - old cables being recovered.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20100_.jpg)
Existing services - cables being recovered from the existing bridge area.
![Backfilling around the underfilled structure](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20124_.jpg)
Underfilled section of the existing structure being backfilled and buried.
![Electricity Cable being spiked.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20131_.jpg)
Electricity cable being "spiked" with a bullet through the cable.
![Excavator creating the embankment over the infilled deck.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20140_.jpg)
Underfilled structure being backfilled and buried.
![Excavator clearing the remaining black from the deck.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20150_.jpg)
Surfacing being removed from the existing bridge deck - Note the existing gas main on the bridge still "live" blue line.
![Crane platform created between the old and new structures](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20151_.jpg)
Crane platform being created between the new and existing structure ready for a 100t crane.
![New Gas main being installed over the bridge.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20169_.jpg)
New Gas Main being installed across the new bridge deck.
![Gas main connected up and old main drilled and made dead.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20195_.jpg)
New Gas main being made "live". Note the existing main has been drilled at tapped to ensure that it is empty of Gas.
![Brick Parapet being pulled over from the bridge deck](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20199_.jpg)
Parapet being demolished on the bridge deck.
![Excavator on the deck clearing parapet.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20203_.jpg)
Excavtor pulling in the parapets and clearing the deck.
![SGB Parapet system installed.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20210_.jpg)
Parapet removed - SGB combi-safe fence erected on the edge.
![Last of the services being removed from the deck.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20213_.jpg)
Gas Main removed final section of cables being ripped out and cleared from the deck.
![Excavators working together to pull in the parapets](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20229_.jpg)
Double team - excavators on the bridg pulling in the Southern Parapet.
![A small tug and the wall falls over very controlled not one brick on the track below.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20230_.jpg)
Parapet pulled over and pulled in - Not one brick landed on the track.
![Dene Illingsworth putting up the edge protection.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20233_.jpg)
Dene Illingsworth - Senior Foreman - installing edge protection Combi- safe.
![Plate load test using a Moxy as dead weight](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20238_.jpg)
Plate load test on the crane platform - using the ADT axle.
![Holemasters setting up on the deck to cut and drill the deck.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20243_.jpg)
Polyethene sheeting laid on the track - Holemaster start cutting up the deck panels.
![Deck being cut up and holes for chains being drilled.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20248_.jpg)
Deck slabs being cut up - lifting holes for the chains drilled in the bridge deck.
![Cutting and drilling progressing on the deck](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20257_.jpg)
Holemaster - cutting the bridge deck up.
![Last of the holes being drilled for the lifting chains](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20260_.jpg)
Portable drilling rig being used for finishing the holes on the deck.
![Inspection of drilling and cutting from track level looks - good to go](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20265_.jpg)
View on the underside of the bridge deck - looking at holes for lifting points.
![Anchorage bolts and running line installed on the deck.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20271_.jpg)
Ends of the slabs fully exposed. Fall arrest system set up on the bridge deck.
![100t Crane with spreader beam lifting out the first unit.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20276_.jpg)
100T Crane set up lifting out the precast units.
![Chains locked into the cut outs to stop them slipping.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20285_.jpg)
Pre-cast units being lifted out - Note the chains in the lifting holes.
![Work progressing to remove the units one at a time](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20288_.jpg)
Crane lifting pre-cast units from the deck.
![Once each unit is removed it is stacked up ready for removal and crushing by the excavators.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20296_.jpg)
Cranes - stacking up the units on the bidge deck.
![Last unit being lifted clear Note the running fixing at the centre](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20312_.jpg)
David Millar on the last unit getting ready to lift it out.
![Phase 1 Complete.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20314_.jpg)
With the final section removed the crane was de-rigged ready for the next visit.
![Header beam being lifted (worst case lift)](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20328_.jpg)
2nd crane visit - 10t lift cross beam being lifted free.
![Beam lifted clear from the top of the trestles](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20331_.jpg)
Cross beam being lifted free - note the dowels on the underside.
![Holemasters using a band saw to cut the legs](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20339_.jpg)
Holemasters - using a Bandsaw to cut through the legs of the trestle.
![1st leg cut - Chains around the first set of legs - cutting the second leg](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20343_.jpg)
1st Trestle set up for lifting. Holemaster cutting the trestle legs.
![Crane lifting the first set of legs to the laydown area](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20345_.jpg)
Cut free trestle being lifted on to the deck.
![2nd Set of legs being cut](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20348_.jpg)
2nd Trestle being cut free.
![Band saw being used to cut the 2nd leg](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20349_.jpg)
Band Saw cutting the trestle legs free.
![2nd Trestle being lifted out.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20351_.jpg)
Trestle cut and lifted out.
![Final trestle being cut through](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20360_.jpg)
Last trestle being cut free for lifting.
![Crane lifting out the final trestle](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20363_.jpg)
Completed cutting works last trestle gets lifted out.
![Trestles cut down and laid down on the deck ready for removal.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20368_.jpg)
Trestle and header beam laid out on the bridge ready for removal.
![North Abutment set up ready for cutting.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20373_.jpg)
View on the abutment ready for remodelling - note the string line on the wall showing the cut line.
![Holemasters installing a wall saw to cut the brickwork.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20384_.jpg)
Track saw being used by Holemaster to cut a saw line on the abutment wall.
![Scaffold set up with wall saw cutting the top section.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20392_.jpg)
Saw cut on the existing abutment - scaffold erected to enable the final section to be cut.
![Ivor King Movax rig removing the sheet piles](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20408_.jpg)
Ivor King Movax rig removing the sheet piles from the wingwall.
![Braithwaite Demolition clearing trestles of the bridge as Ivor King finish and move away.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20431_.jpg)
Braithwaite demolition clearing the trestles of the bridge deck.
![Excavator pulling in the Parapets](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20438_.jpg)
Parapets being removed on the arch span approach.
![Parapets removed.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20446_.jpg)
Parapets removed from the arch spans.
![Arch span being broken down](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20448_.jpg)
Arches being broken down.
![Central span arch being broken down](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20459_.jpg)
Central arch span being broken down.
![Arch span being broken down ash fill core can be seen.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20467_.jpg)
Works progressing across the arch spans.
![Arch being broken down.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20474_.jpg)
Arch being broken down - note the ash infill and just how loose the bricks in the arch are as it is broken free.
![Concrete capping beam being pulled off by two excavators](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20497_.jpg)
Abutment concrete cill beam being removed - two excavators being used to pull it over - Note the plywood protection on the track.
![Break down of the final section of arch](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20501_.jpg)
Abutment being pulled over and broken down.
![Clear up of the brickwork](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20509_.jpg)
Bricks broken down and loaded away to the crushing yard.
![Clear up in progress with North abutment broken down.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20518_.jpg)
Bridge abutments removed - bricks cleared up.
![North Abutment cut down ready for coping stones](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20523_.jpg)
Abutment cut and the top section of abutment pulled back.
![Crane lifting in stone copings reclaimed from the bridge parapets](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20527_.jpg)
Crane lifting in the Stone cop stones - scaffold being used for access.
![Crane and skip being used to break down the final section of the foundations](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20528_.jpg)
Crane used with rock skip - operatives breaking out the final 500mm depth of the trestle legs.
![Pallasade fence being installed between the track and the canal.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20544_.jpg)
Profile of the new canal being formed - view on the pallisade face.
![Fence being installed between the canal and the railway.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20549_.jpg)
View on the canal bed - sheet pile and cop wall - pallisade fence.
![Fence installed on the North Abutment.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20550_.jpg)
Pallisade fence installed on the North abutment.
![Final Project completed with fences in place. New bridge fully open.](http://www.dbmbridges.com/web_images/project_no_24__-_bacs_2-5__20552_.jpg)
Completed new bridge with finished fences - bridge fully removed.
Page under construction...
| |
| | |
|
|
|
|
|